Columbia Independent School officially opened the 2009-10 school year on August 25. Completing this project on time took the full effort and cooperation of construction workers, CIS staff members and a great crew of volunteers. In addition to a beautiful new school, we built many relationships over the course of this project. It's been an experience none of us will soon forget. |


|
August 17, 2009
- Finishing touches are being carried out this week by contractors and CIS staff and volunteers.
- Dave Griggs is scheduled to finish flooring this week.
- Teachers and volunteers continue to set up classrooms for Friday orientation and the first day of school next week.
|


|
August 10, 2009
- Final door hardware is being installed.
- Finish floor installation continues.
- Interior/exterior glass is being installed this week.
- Final punch-out work is underway.
- CIS volunteers have started moving items into classrooms.

|


|
August 3, 2009
- New vinyl strip wood floor is being installed in the Fitness Room and Play Room.
- New exterior doors and interior glass are being measured and installed.
- 120,000 square feet of new drywall is complete.
- 20,000 lineal feet of new voice/data low-voltage cables have been pulled into rooms.
- Many tradesmen have completed their scope of work on the project.
- Final clean and punch-out work starts this week.

|


|
July 27, 2009
- The 7-day work weeks continues as the project nears completion.
- CIS staff members are moving items into middle and upper school rooms.
- Finish flooring is being installed in the administration area.
- All exterior concrete work is done.
- Drywall finish work will be completed this week.
- All remaining ceiling grids will be installed this week.
|


|
July 20, 2009
- Hercon hosted a job-site barbeque for some 80 construction workers and CIS staff members last Friday. Everyone enjoyed the great weather and a break from the daily grind.
- CIS staff members are setting up furniture in lower school classrooms. Middle and upper school furniture move-in begins next week.
- Finish flooring is being installed in the upper school.
- Seven-day work week will continue, as needed, through remainder of project.
- New HVAC units are being tested and balanced.
 |
 |
July 13, 2009
- Seven-day work week continues.
- All rooftop HVAC units have been set.
- Installation of finish flooring in the middle school starts this week.
- CIS has moved furniture and supplies into lower school rooms.
- Upper school science lab equipment is being installed.
- Metal stud framing is complete and drywall hanging is scheduled to finish this week.
- Ceiling grid installation is 80% complete.
- Approximately 50,000 square feet of new interior ceiling insulation has been installed to date.
|


|
|
 |
June 29, 2009
- 15,000 feet of new voice/data wiring has been pulled into lower and middle school classrooms.
- Half the new rooftop HVAC units have been set.
- Ceiling tile and finish floor installation is underway in the lower school.
- More than 100,000 square feet of new wall drywall has been installed.
- Cabinets have been set in the lower school.
- Sinks are being installed in the lower school.
- Drywall is being installed in the upper school science labs and classrooms.
|
 |
June 22, 2009
- 7-day work week continues to maintain schedule.
- Metal stud wall framing is complete.
- New HVAC roof-top units are being set this week.
- Drywall is being hung in last areas of the building.
- Finish flooring starts in lower school this week.
|


|
June 15, 2009
- Crews have begun working 7 days a week to stay on schedule.
- 80,000 square feet of drywall have been installed.
- Ceiling grids and ceiling lights are being installed in lower school classrooms.
- Floor preparation has begun in lower school classrooms.
- Science lab framing, plumbing and electrical in-wall rough-ins are complete.
- Metal stud wall framing and rooftop
HVAC unit structural support framing are scheduled for completion this week
|


|
June 8, 2009
- More than 10,000 man hours of labor have gone into the project to date.
- Lower school classrooms are being painted.
- Above-ceiling mechanical, electrical and plumbing items are being installed throughout the building.
- New R-30 ceiling insulation is being installed in the lower and middle school wings.
- Some 3,200 lineal feet of new partition walls have been built.
- Plumbers and electricians are working on science labs.
|

|
June 1, 2009
- 50 to 60 construction workers are on site daily.
- To stay on schedule, some work is being done on Saturdays.
- Lower school classroom walls are being painted.

|
 |
May 25, 2009
- Work has begun on under-slab plumbing for the upper school science labs.
- Frame walls are being built in the science lab, cafeteria and administration areas.
- Lower school ceilings are being insulated.
- Drywall is being finished and prepped for painting in the lower school area.
- Above-ceiling mechanical, plumbing and electrical work continues through out building.

|


|
May 18, 2009
- Framing of new walls is nearly complete.
- Drywall is being hung in the lower school and will be ready for prime painting later this week.
- Work is proceeding on installation of mechanical systems.
- A new concrete sidewalk has been poured on the west side of the building.

|
 |
May 11, 2009
- New wall construction is 50 percent complete.
- Sidewalks are ready to be poured.
- Work continues on installation of mechanical systems.

|
  |
May 4, 2009
- Major architectural demolition work on the 62,000-square-foot building is now complete.
- Nine semi-trailers have been filled with desks, file cabinets and other furnishings that will be used by the school.
- Excavation work is underway for installation of underground plumbing lines.
- New wall construction is 25 percent complete.
- In-wall electrical installation is in progress.
- Overhead ductwork is being installed.
|